“ We rely heavily on Asta for forecasting into the future,” Ashley explains.“ We can see months ahead which materials we’ re going to need, when we need to order them, and what quantities our plants will need to produce.”
That level of visibility allows Milestone to avoid supply shortages while taking advantage of favorable purchasing opportunities before prices rise. Those forecasting capabilities proved especially valuable during the Covid-19 pandemic. When supply chains became unpredictable and material availability tightened, Milestone already had visibility into future material requirements. That allowed the company to purchase and stockpile critical materials before shortages became severe.
At the same time, pandemic-related traffic reductions dramatically accelerated several highway projects. Projects originally planned over multiple construction seasons suddenly could be completed in a fraction of the time because interstate closures became possible. Instead of being caught unprepared, Milestone was able to adjust schedules quickly, identify changing material requirements and secure the necessary resources to capitalize on those opportunities.
“ We were able to see that our timelines had changed dramatically,” Ashley says.“ Because we already had everything planned in the system, we knew what materials we needed and could start obtaining them much earlier.”
Better resource management = better workforce retention
Perhaps the most significant business benefit has come through workforce planning. Like much of the construction industry, Milestone faces ongoing labor shortages. And losing experienced crews can have negative long-term consequences.
Powerproject gives management visibility into future workload across the organization, allowing crews to be reassigned between projects rather than laid off during temporary slow periods. So, instead of losing experienced workers to other contractors, Milestone can proactively identify upcoming projects where those crews will be needed. The ability to preserve experienced crews has become increasingly important as qualified construction labor becomes more difficult to replace.
“ It has undoubtedly helped us retain our workforce,” Ashley notes.“ We can see where a crew may have a gap coming up and move them to another project instead of losing them.”
More recently, Milestone has transitioned from its original enterprise environment to Asta Vision. The implementation was phased over several years, beginning with internal administrators before expanding across the company. Today, nearly all scheduling personnel use the Vision platform.
One of the biggest improvements has been project version control. Previously, changes made by one user could inadvertently affect other schedules. Vision’ s project checkin / check-out functionality allows users to work independently while maintaining a complete history of changes. Administrators can also easily see who modified a project, when changes were made and, if necessary, restore previous versions. Those safeguards have increased user confidence and encouraged more frequent schedule updates.
“ People are much more willing to update their schedules now because they know they’ re not going to accidentally affect everyone else’ s work,” Ashley says.
Producing better schedules
The benefits also extend beyond technology. As project managers gain experience using Powerproject, they become better planners. The software’ s dependency management and connected scheduling logic make it easier to identify sequencing errors before construction begins. Even when collaborating with outside